Are dispute adjudication decisions binding and enforceable, even if incorrect?

  • Legal Development 07 February 2022 07 February 2022
  • Africa

  • Projects & Construction

In many standard form construction contracts, such as FIDIC and the NEC3 Engineering and Construction Contract, the first mechanism to resolve any dispute between parties is to refer the dispute to adjudication.

Background

Adjudication is intended to be a speedy and less costly means of settling a dispute on an interim, yet binding basis. The final mechanism to resolve a dispute is to refer the dispute to arbitration and the arbitrator is empowered to revise the award of the adjudicator.

Summary

The Supreme Court of Appeal (SCA) has recently in the case of Framatome v Eskom Holdings SOC Ltd[1] reaffirmed that an adjudicator’s award is binding and enforceable, notwithstanding that the award could subsequently be revised at arbitration.

This is in keeping with previous SCA landmark decisions such as Ekurhuleni West College v Segal and Another[2] and Radon Projects (Pty) Ltd v NV Properties and Another[3], which upheld the firm principle that an unsuccessful party cannot simply refuse to perform in terms of an adjudicator’s award on the basis that it is dissatisfied with the award, delivered a notice of dissatisfaction and has referred the dispute to arbitration.

The relevant case

Eskom (the Employer) and Framatome (the Contactor) concluded an NEC3 Engineering and Construction Contract for the replacement of the Steam Generators at Koeberg Nuclear Power Station for Unit 1 and 2 (the Contract). The Contract provided for adjudication as the first procedure in resolving disputes between the parties.

A dispute arose between the parties in respect of a compensation event notified by the Project Manager to Eskom.

Framatome referred the dispute to adjudication and the adjudicator found in favour of Framatome on the basis that the Project Manager’s instruction to Eskom was a compensation event which needed to be assessed by Eskom (Decision 7). Surprisingly, Eskom did not issue its notice of dissatisfaction for Decision 7, but simply ignored the adjudicator’s award.

A further dispute was referred to adjudication by Framatome which dealt with the assessment of the compensation event in Decision 7, in which Eskom refused to provide an evaluation of the compensation event. The adjudicator concluded that Eskom had failed to make a full assessment in due time as required by Decision 7 and that Framatome’s proposed quotation was deemed to be accepted in terms of the deeming provisions of the Contract (Decision 11).

Subsequently, Eskom notified the adjudicator and Framatome of its dissatisfaction with Decision 11, which prompted Framatome to institute enforcement proceeding against Eskom at the Gauteng High Court.

The enforcement application

Eskom was successful in resisting the enforcement of the adjudicator’s decision on the basis that the adjudicator in Decision 11 was found by the High Court to have acted outside his terms of reference and to have exceeded his jurisdiction, by deciding issues that were not referred to him.

Accordingly, Framatome appealed to the SCA.

The SCA decision

The SCA reasoned that, in the final analysis, the question to be asked was whether the adjudicator’s determination was binding on the parties – the answer to which turned on whether the adjudicator confined himself to a determination of the issues that were put before him by the parties. If he did so, said the SCA, then the parties were bound by his determination, notwithstanding that he may have “fallen into error”.

In that regard, the SCA held as follows:

  • The adjudicator, in Decision 11, formulated the dispute as it was referred to him. At no stage did he depart from the “real dispute” between the parties, but had instead made his determination in accordance with what the parties had contemplated and appreciated.
     
  • Only an arbitral tribunal could revise an adjudicator’s decision and because the decision had not been revisited, it remained binding and enforceable.
     
  • Eskom was ordered to give full effect to the adjudicator’s decision and to make payment to Framatome.

In arriving at this conclusion, the SCA referred to an excerpt of Hudson’s Building and Engineering Contracts, noting that:

‘It should only be in rare circumstances that the courts will interfere with the decision of an Adjudicator, and the courts should give no encouragement to an approach which might aptly be described as “simply scrabbling around to find some argument, however tenuous, to resist payment”.’[4]

Key points

The SCA has once again made it clear that disputed adjudication awards are binding, unless and until the dispute is revisited at arbitration.

  • Parties to construction contracts would be well advised to apprise themselves of the applicable dispute resolution provisions. A party should not agree to refer a dispute to adjudication on the assumption that if the adjudicator decides against them, they may simply ignore the decision and resist performance pending final determination of the dispute at arbitration.

Feel free to reach out to us if you would like to discuss any similar matters.

End

Stay up to date with Clyde & Co

Sign up to receive email updates straight to your inbox!