Australia's Data Centre Boom: Managing Professional Liability Risk

  • Insight Article 2026年11月24日 2026年11月24日
  • 亚太地区

  • Regulatory movement

  • 保险和再保险

Data centres are among the largest infrastructure projects being delivered in Australia, with developments often exceeding AUD$1 billion. Their supporters tout them as driving productivity and prosperity, while others question whether electricity generation and transmission can expand quickly enough to support their projected growth.

Governments increasingly regard data centres as strategic national infrastructure, which has resulted in greater regulatory scrutiny. In July 2026, Australia’s Prime Minister Anthony Albanese announced proposed mandatory national standards for large-scale data centres, including requirements relating to their location and energy and water usage. The most noteworthy proposal is that future large-scale data centres may be required to underwrite their own new power supply, fund their own grid connection costs and contribute at least as much energy to the grid as they consume.[1]

At the time of writing, Australia has approximately 162 operational data centres, with development concentrated in New South Wales and Victoria. The sector continues to expand, with approximately 90 further data centre projects in the pipeline.[2] To support this growth, significant investment is being made in enabling infrastructure. Fibre projects such as SUBCO’s Sydney Melbourne Adelaide Perth cable and Google’s Australia Connect initiative are increasing network capacity and linking Australia’s cities.[3] At the same time, an increasing proportion of developments are being built outside major metropolitan centres, reflecting the need for access to suitable land, renewable energy resources and supporting energy infrastructure. As a result, access to energy infrastructure has become as important as access to telecommunications infrastructure, influencing both site selection and project viability.

The pace of development is placing increasing pressure on planning, design, procurement and commissioning. As projects get larger and more complex, the potential size of claims arising from design, coordination or delivery failures also grows.

The Severity Challenge for Professional Liability Insurers

From an insurer's perspective, the defining trend in data centre construction is not necessarily a greater number of professional liability claims, but the potential for significantly larger claims.

Claims typically arise from errors and omissions in planning, design, construction and commissioning. Severity is driven by the high degree of interdependence between systems and the potential for significant delays when something goes wrong. These projects involve multiple consultants and contractors, meaning disputes often draw numerous parties into proceedings when issues arise, thereby prolonging disputes and increasing costs.

The range of participants reflects the complexity of these projects. It commonly includes architects, civil, structural and mechanical engineers, project managers, construction contractors, specialist consultants and commissioning experts.

When assessing risk, insurers tend to look beyond contractual responsibility. They will also consider whether the consultant or contractor has relevant data centre experience, given the technical demands of these facilities.

Risk Allocation and Standards of Responsibility

Contractual terms also materially affect risk. Fitness for purpose obligations expose designers to liability even where they have exercised reasonable skill and care. Requirements to perform to the standard of an experienced data centre designer likewise warrant close attention. Major data centre projects commonly include detailed performance requirements relating to critical systems and operational outcomes. Where developments incorporate renewable energy generation and battery storage infrastructure, contractual requirements may extend to generation capacity, storage performance and degradation thresholds.

Delays in installation or commissioning may therefore have consequences beyond programme impacts, potentially affecting compliance with contractual performance criteria. From an operational perspective, disputes are likely to focus on whether uptime, resilience and other service level requirements have been achieved.

The Additional Complexity of AI-Ready Data Centres

AI-ready data centres add another layer of complexity. They rely on graphics processing units rather than central processing units, creating higher power densities, larger racks, more cabling and the need for advanced cooling. Traditional enterprise data centres commonly operate with rack densities of 10 to 20 kilowatts, whereas AI infrastructure may operate at 80 to 120 kilowatts per rack or more.[4] This increases the importance of effective system integration.

Outages can have more significant consequences as data centres are increasingly used for AI training and inference workloads, increasing the potential severity of professional liability claims.

NEXTDC’s S7 campus in Western Sydney is a useful illustration.[5] It is being developed to support large-scale graphics processing unit clusters, with high-density racks that require substantial power and thermal management. Its intended use of advanced liquid-cooling systems, such as direct-to-chip solutions, reflects a shift towards more complex and performance driven infrastructure.

Emerging Sources of Professional Liability Exposure

Against that backdrop, several recurring risks are emerging. These include achieving performance criteria, managing fire risk associated with lithium-ion uninterrupted power systems and diesel generation, addressing the risk of escaped liquids from complex cooling networks[6], complying with obligations under the Security of Critical Infrastructure Act 2018, delivering designs that are capable of future upgrades, managing interfaces between complex systems, and completing commissioning to ensure the facility is ready for operation.

Performance risks may be heightened where projects depend on the integration of power generation, battery storage and grid infrastructure. Although renewable energy and battery technologies can reduce grid reliance, network supply remains a critical dependency for many data centres. The design, integration and reliability of these interrelated systems can therefore become important sources of professional liability exposure where performance requirements are not satisfied.

Delivery, Supply Chain and Modular Construction Challenges

Delivery risk is also increasing. While supply chain pressure affecting specialised and long-lead-time equipment remains relevant, delays associated with grid connections, energisation, and supporting energy infrastructure may present an even greater challenge to project delivery.

Given the power requirements of modern facilities, delays in securing network connections or associated approvals can affect construction sequencing, commissioning and operational readiness. Shortages of skilled labour, the use of off-site modular construction and equipment substitution driven by procurement constraints add further complexity.

Prefabricated power and cooling modules and server racks based on proven designs can improve speed and consistency, but they also introduce additional exposures. These include supplier insolvency, interface failure, transport and storage issues, and latent defects. Late design changes or substitutions can disrupt coordination of mechanical, electrical and plumbing systems, affect construction sequencing, and require further testing and certification. In some cases, defective or delayed modules may hold up the broader programme.

Insurance and Underwriting Considerations

For construction professionals, these risks reinforce the importance of insurance that responds to defective design, system integration failures, commissioning issues and performance related claims. When disputes arise, they are likely to involve multiple parties and often include arguments about the respective roles of design and workmanship.

For professional indemnity underwriters, consequential loss remains a central concern. A relatively small issue in a critical system can delay commissioning or lead to outages with significant downstream consequences. Claims may therefore focus on performance outcomes, such as uptime and resilience, rather than physical defects alone, increasing exposure to consequential loss.

Standard policy limits may not be sufficient for projects at this scale, making project specific or owner arranged cover an important consideration.

When Technical Failures Become Liability Exposures 

Failures in critical data centre systems can have consequences extending well beyond the immediate technical issue, including property damage, business interruption and regulatory scrutiny. These incidents highlight the design, coordination, commissioning and operational considerations that may arise when critical infrastructure fails.

Fire and electrical resilience

In March 2021, OVHcloud's SBG2 data centre in Strasbourg was destroyed by fire. No one was injured, but the incident caused extensive property damage and widespread service disruption, taking websites, domain names and IP services offline. The subsequent investigation found that the fire originated within SBG2's electrical power infrastructure, including rooms housing UPS equipment and lead acid batteries. Moisture near inverter equipment was identified as a possible contributing factor, although investigators were unable to determine the precise ignition source. The investigation also found that the scale of the loss was exacerbated by the absence of automatic fire suppression and difficulties de-energising equipment during the emergency. The report did not identify a definitive cause of the fire or attribute fault to any particular engineer, contractor or other party.[7]

For professional liability purposes, the incident demonstrates how electrical design, fire compartmentation, suppression strategy, ventilation, emergency isolation and operational procedures can interact. A claim following a similar loss may test whether those interfaces were adequately designed, coordinated, documented, maintained and commissioned.

Cooling resilience

During the July 2022 UK heatwave, cooling failures affected London facilities operated by Google Cloud and Oracle. Oracle reported that two cooling units failed when required to operate above their design limits, causing temperatures to rise and systems to shut down protectively. Google likewise powered down equipment after a cooling-related failure; its later incident review described the simultaneous failure of multiple redundant cooling systems.[8]

This highlights the importance of validating ambient design assumptions against foreseeable extremes and testing whether nominal redundancy is vulnerable to a common mode event. Designers and commissioning teams may need to demonstrate adequate capacity, controls, alarms, failover logic and recovery procedures not only for normal operation but also for concurrent equipment failures and increasingly severe heat. 

Commissioning discharges

In 2026, a bacterium (cupriavidus gilardii) was detected in Cheyenne, Wyoming's reclaimed-water system after wastewater from fill-and-flush operations at a Meta data centre project entered the municipal network. The bacterium was not found in drinking water, but parts of the reclaimed water system were temporarily shut down while remediation was undertaken, and industrial discharges from the site were stopped and hauled offsite.[9]

The incident illustrates that professional liability exposure may arise during commissioning, before a facility begins normal operations. Design and delivery teams may face scrutiny over flushing plans, water treatment and sampling, discharge approvals, temporary connections, contractor interfaces and communication with utilities and regulators. Pollution exclusions and the boundary between professional services, construction activities and operational control may also become important coverage issues. 

Outages and consequential loss

The financial consequences of an outage can far exceed the cost of repairing the initiating fault. After British Airways' May 2017 IT failure, at least 75,000 travellers were affected over three days and IAG initially estimated the cost at approximately £80 million in lost revenue and passenger accommodation, rebooking and compensation. At the time, IAG said the failure appeared to have followed the disconnection and reconnection of power at a data centre, while an independent investigation remained under way.[10]

A different failure mode arose in AWS's US-East-1 region in October 2025. AWS reported that a latent race condition in automated DNS management for DynamoDB resulted in DNS resolution failures for the regional endpoint. The initial fault cascaded into EC2 launch and network load-balancer recovery issues and disrupted dependent services for many hours.[11]

Together, the incidents show how a small human, control or software configuration failure can propagate through interdependent systems. In claims, attention is likely to centre on change control, automation safeguards, redundancy, dependency mapping, testing, disaster recovery and whether consequential-loss limitations align with the exposure. They also show why losses arising from a modest initiating defect can greatly exceed the cost of repair.

Conclusion

Australia's data centre boom presents significant opportunities but also creates a rapidly evolving risk environment for construction professionals and insurers. As data centres become larger, more power-intensive and increasingly dependent on the successful integration of complex digital and energy infrastructure, professional liability exposures are likely to become more severe.

For underwriters, consultants and contractors alike, attention to project experience, contractual risk allocation, system integration and performance obligations will be critical to managing the risks.

Clyde & Co’s Professional and Financial Disputes team regularly acts for professionals and their insurers in complex professional liability disputes, including claims arising from major construction and infrastructure projects. Drawing on that experience, the team is well placed to assist professionals and insurers in assessing and managing the emerging liability and coverage risks associated with data centre development, from the early stages of a claim through to resolution of complex, multi-party disputes.