Fair Competition Tribunal Partly Overturns FCC’s Prohibition of Anheuser-Busch InBev SA/NV –TDL Merger
Tanzania: 2025 Amendments to the Electricity (Development of Small Power Projects) Rules, Government Notice No. 491 of 2020
-
Insight Article 03 December 2025 03 December 2025
-
Africa
-
Regulatory movement
-
Projects & Construction
On 31 October 2025, the Government of Tanzania published the Electricity (Development of Small Power Projects) (Amendment) Rules, GN No. 640 of 2025 (the SPP Amendments) to amend the provisions of the Electricity (Development of Small Power Projects) Rules G.N No. 491 of 2020 (the SPP Rules).
The SPP Amendments aim to streamline the development of Small Power Projects (SPPs) and Very Small Power Projects (VSPPs), strengthen oversight by the Energy and Water Utilities Regulatory Authority (the EWURA) and Rural Energy Agency (REA), update strategic area criteria, revise Standardized Power Purchase Agreements (SPPAs) and introduce enhanced compliance obligations for developers.
These changes have significant implications for project developers, investors, and distribution network operators (DNOs), particularly in licensing, project structuring, and contractual arrangements.
In this legal update, we review key changes introduced under the SPP Amendments:
| Provision | SPP Rules | SPP Amendments |
|---|---|---|
| Rule 3: Interpretation |
Defined the following terms: (a) "Small power producer" previously defined as an entity producing electricity with a generating capacity between 100kW up to 10 MW at a single site using renewable energy, fossil fuels, a cogeneration technology, or some hybrid system combining a renewable fuel source with other fuel sources mentioned above and either sells the generated power at wholesale to a DNO or at retail directly to a customer or customers; (b) "Small power project developer” means an entity generating electricity in the capacity between 100kW up to 10 MW using renewable energy, fossil fuels, a cogeneration technology, or some hybrid system combining fuel sources and either sells the generated power at wholesale to a DNO or at retail directly to a customer or customers, and the development may have an installed capacity greater than 10 MW but shall only export power at the interconnection point not exceeding 10 MW, and the term “Small Power Producer” shall be construed accordingly; (c) "Avoided cost" was previously defined as the cost the DNO have incurred when it generates electricity itself or sourced it from another source; and (d) “Eligible customer” means any person who is authorised by the EWURA to enter into a contract for the supply of electricity directly with any person licensed to generate electricity |
Expands, replaces and clarifies various definitions under the SPP Rules including the following: (a) Amends the definition of “Small Power Project Developer” by limiting fossil fuels in hybrid systems to 25% of total capacity, updating “renewable energy” to “renewable energy sources,” and removing the previous allowance for installed capacity above 10 MW with export limits; (b) Amends the definition of “Small Power Project Developer” by limiting fossil fuels in hybrid systems to 25% of total capacity, updating “renewable energy” to “renewable energy sources,” and removing the previous allowance for installed capacity above 10 MW with export limits; (c) Amends the definition of “Avoided Cost” by replacing the previous broad description with a specific cost-comparison approach. The new definition now refers to the incremental cost savings realized by a DNO when purchasing electricity from another generator instead of generating it itself, thereby clarifying how avoided cost is calculated; and (d) Amends the definition of “Eligible Customer” by changing the category of the contracting counterparty. The new definition permits an eligible customer to contract directly with a person licensed to generate electricity, replacing the earlier requirement that the contract be with a person licensed to supply electricity. |
| Rule 4: Determination of strategic areas |
Rule 4(2) provided specific requirements for a SPP developer to demonstrate how its proposed area has a “technical benefit.” Rule 4(3) of the SPP Rules restricted SPP developers from developing projects in areas not declared as strategic or where the proposed total installed capacity exceeded the maximum demand of the local distribution network. Subrule 6 of the SPP Rules required the DNO to immediately publish in widely circulated newspapers in Tanzania a list of areas determined to be of strategic nature. Subrule 8 of the SPP Rules previously exempted VSPP projects already under construction stage from compliance with Rule 4 of the SPP Rules. |
Amends Rule 4 of the SPP Rules by adding an additional requirement under subrule 2(c) requiring proposed projects to offer additional commercial or technical benefits to the DNO, subject to DNO determination and approval by EWURA. Subrule 3 has been amended to restrict SPP developers to only developing projects in areas officially declared as strategic. Subrule 6 is amended to require DNOs to publish the list of strategic areas in the month of July annually in widely circulated newspapers in Tanzania, ensuring transparency. Lastly Subrule 8 of the SPP Rules is now deleted. Therefore, all VSPP projects are required to comply with Rule 4 of the SPP Rules without exception and irrespective of the development stage. |
| Rule 5: Criteria for development of VSPP’s |
Under the SPP Rules, the development of a VSPP was strictly regulated. No person could develop a VSPP without first applying for and obtaining a letter of support from the Ministry responsible for electricity matter (the Ministry). The application had to be submitted in writing accompanied with: (a) a copy of a valid business plan; |
Adds a new requirement in relation to the VSPP application process requiring mini-grid developers to obtain an endorsement from the REA before submitting their applications with EWURA. |
| Rule 6: Submission of quarterly reports | Rule 6, of the SPP Rules required a VSPP developer to submit quarterly progress reports to the EWURA and the Ministry after receiving the letter of support, and any letter of support would automatically expire if no report was submitted for more than six (6) months. | Deletes Rule 6 of the SPP Rules, therefore, VSPP developers are no longer required to submit quarterly progress reports or reapply for a letter of support from the Ministry under this Rule. |
| Rule 7: Appeal against decision of DNO | Rule 7 of the SPP Rules allowed a project developer who was aggrieved by a DNO’s decision to appeal to the EWURA. | Amends Rule 7 of the SPP Rules, by permitting a developer to refer the matter to the EWURA instead of filing an appeal, while still preserving the developer’s right to have the EWURA review the decision. |
| Rule 35: Signing of SPPAs | Under the SPP Rules, Rule 35 required that Power Purchase Agreements (PPAs) between a DNO and a SPP be executed using the standardised form prescribed in the Third Schedule of the SPP Rules. The rule also provided guidance on signing procedures, a standard term of 20 years, interconnection requirements, and allowed renegotiation of existing agreements. |
The SPP Amendments revise Rule 35(1) by requiring that any PPA entered into between a DNO and a seller for the sale of electricity must be executed in the SPPA form as prescribed by EWURA, replacing the previous reference to the Third Schedule. In addition, the SPP Amendments introduce new subrules (7), (8), and (9), which: (a) Require that a SPP developer and a DNO sign the SPPA approved by EWURA without substantive amendments; (b) Empower EWURA to issue standardised addenda to address emerging technologies or project-specific innovations, specifying technical and operational requirements; and (c) Mandate that parties to existing SPPAs adopt such addenda where required, ensuring consistency, adaptability, and alignment with evolving industry standards. |
| Rule 36: Licensing Requirements | Previously, Rule 36 required an SPP developer, after signing a standardized PPA with a DNO, to apply for a licence from EWURA in accordance with the Electricity (Generation, Transmission and Distribution Activities) Rules 2019. | The SPP Amendments amend Rule 36 by removing the reference to the year “2019.” The provision now requires SPP developers to apply for a licence in accordance with the Electricity (Generation, Transmission and Distribution Activities) Rules, without restricting the reference to the 2019 version of the Electricity (Generation, Transmission and Distribution Activities) Rules. |
| Rule 58: Reporting Requirements | Previously, Rule 58 of the SPP Rules required SPPs, VSPPs, and small distributors to submit an annual report to EWURA within 120 days after the end of the financial year, using the prescribed format. | The SPP Amendments add Subrule (3), introducing an additional compliance obligation that every SPP developer must also sign a Performance Agreement with EWURA, alongside the existing requirement to submit annual reports. |
Conclusion
The SPP Amendments reflect a policy shift toward a more structured and transparent regulatory environment for small scale power generation. By introducing standardised agreements and removing outdated reporting requirements, the amendments reduce ambiguity and administrative inefficiencies.
However, SPP developers must adapt quickly to new compliance obligations, particularly the requirement to sign a Performance Agreement with EWURA and adhere to fossil fuel limits in hybrid systems. These changes may increase upfront regulatory engagement but will likely enhance investor confidence and reduce contractual disputes in the long term.
End



